North Cyprus Tourist Board - Kavankoy 2 apt. owner
North Cyprus
North Cyprus > North Cyprus Forum > Kavankoy 2 apt. owner

Kavankoy 2 apt. owner

North Cyprus Forums Homepage

Join Cyprus44 Board | Already a member? Login

Popular Posts - List of popular topics discussed on our board.

You must be a member and logged in, to post replies and new topics.



High Priest


Joined: 12/04/2008
Posts: 148

Message Posted:
12/04/2008 22:53

Join or Login to Reply
Message 1 of 16 in Discussion

Hi, we are new board members and found the info interesting. We visited kavanlar phase 2 site in March and were encouraged to see things progressing. We met with Ilker and he garaunteed completion at the end of May this year. He passed on information about the maintainance company, MEPS, but no costing.



orangekazzie



Joined: 31/07/2007
Posts: 1091

Message Posted:
12/04/2008 22:57

Join or Login to Reply
Message 2 of 16 in Discussion

Hi High Priest

Welcome to the Forum.

Karen



simbas



Joined: 16/07/2007
Posts: 5943

Message Posted:
12/04/2008 23:15

Join or Login to Reply
Message 3 of 16 in Discussion

hi high priest , welcome , hope you enjoy the postings

regards , simbas



kewen


Joined: 03/08/2007
Posts: 59

Message Posted:
12/04/2008 23:22

Join or Login to Reply
Message 4 of 16 in Discussion

Hi High Priest

We have bought on Phase 4. I know we are in for a a bit of a wait!! but looking at phase 1 it looks like it will be worth it. We haven't heard anything about mep but in the contract ,maintenace fees are quoted as 40.00 per month.



kavenkoy


Joined: 10/04/2008
Posts: 1787

Message Posted:
13/04/2008 07:53

Join or Login to Reply
Message 5 of 16 in Discussion

hi high priest



not wishing to scare you off may this year ,but unless you obtain some divine intervention it will never happen .



we are on phase1 ,the stage you were at in mrach when i also was over i have seen before ,lots still to do and them stages take a very long time .

kavanlar will have learnt a lot from 1 sure enough but i would suggest not before end of year to be completed .



on 3 occasions we were told its nearly ready ,book your flights be ready in 2 months and our final stages took 18months to complete and was over by same time .



meps are ok as what we have seen ,we dont have a pool yet and no communal lighting or stair well lighting in blocks ,we have no shop as it wont now happen ,no security hut as it was never thought through (no toilets or wash for security) ,and this site is finished ?...so meps at £40 per month for atteneding grounds and mopping stairs ...is it great value ?....all in all its great build ,quality good and meps etc have been hit by no meters .......but is that the customers fault ?according to kibtek and builders yes.



our contract on phase1 for meps is 1 year ,kavanlar keep trying to hint its 2,but can tell you we will vote for better service at right price next year



High Priest


Joined: 12/04/2008
Posts: 148

Message Posted:
13/04/2008 10:53

Join or Login to Reply
Message 6 of 16 in Discussion

Hi Kewen



Take a look at 'Kavankoy meps' through google. This appears to be the maintainance company for phase 1 and proposed company for phase 2. It's just good to look and picture the finished product.



High Priest


Joined: 12/04/2008
Posts: 148

Message Posted:
13/04/2008 11:54

Join or Login to Reply
Message 7 of 16 in Discussion

Hi Kavenkoy



If apartments are not sold on phase 1, who is paying that contribution to meps?



Also have you got your pergola and bbq completed on the roof terrace or was that not in the contract?



It has also puzzled me that the no. 1 block on phase 2 appears to be a long way behind the rest. Where was the shop supposed to be?



High Priest


Joined: 12/04/2008
Posts: 148

Message Posted:
13/04/2008 11:58

Join or Login to Reply
Message 8 of 16 in Discussion

Hi Kavenkoy



If apartments are not sold on phase 1, who is paying that contribution to meps?



Also have you got your pergola and bbq completed on the roof terrace or was that not in the contract?



It has also puzzled me that the no. 1 block on phase 2 appears to be a long way behind the rest. Where was the shop supposed to be?



kavenkoy


Joined: 10/04/2008
Posts: 1787

Message Posted:
13/04/2008 12:46

Join or Login to Reply
Message 9 of 16 in Discussion

hi hp



should have had slope roof ,and pergola and it got changed to flat roof because of water tank storage and solar power units .shop was supposed to go under what we call the bandstand ,great shade now for anybody wanting cover ....no power to that bit and we all though we could do communal area or bbq area.



block1 is the owner of the land next door ,very lovely typical tc family ,very welcoming .that was the payment for the land ....



Lemtich



Joined: 15/02/2007
Posts: 1487

Message Posted:
13/04/2008 21:11

Join or Login to Reply
Message 10 of 16 in Discussion

Take all completion estimates with a large pinch of salt, do not book fights in expectation of staying in your apartment. Book into the Almonds, Riverside or Sempati with car hire, sort out your water and electric meters yourself. Ring Ilker if you have problems. Be prepared to snag your apartment after electricity and water are connected not before. get your apartment keys as soon as possible, their are 3 sets, keep 2 and let Ilker have the 3rd set, he will probably loose them.



MEPS maintenance charges cost £52.20 per month, £45 pcm plus 16% KDV (VAT)



All apartments in Phase 1 are sold. See the Kavanlar site plan below.



http://i200.photobucket.com/albums/aa219/Lemtich/room_674.jpg



Lem



kewen


Joined: 03/08/2007
Posts: 59

Message Posted:
13/04/2008 21:48

Join or Login to Reply
Message 11 of 16 in Discussion

Sorry my mistake, I said 40 per month in my earlier post when it actually says 50.00 in the contract.



cooper


Joined: 23/10/2007
Posts: 3386

Message Posted:
14/04/2008 08:08

Join or Login to Reply
Message 12 of 16 in Discussion

Hi Kavenkoy



How do you manage for electric if you have no meter?



Cooper



kavenkoy


Joined: 10/04/2008
Posts: 1787

Message Posted:
14/04/2008 09:20

Join or Login to Reply
Message 13 of 16 in Discussion

hi cooper



because i gave ilker p.o.a in august cos paperwork at kibtek not in order at time .he didnt pay for my meter till novemebr as he was busy ,so i missed "the boat".i have only stayed once for a week and ilker came up trumps sorting me with builders supply .now when i return this summer i have a problem if no meters are installed .



the kind people in lem and janann says they will run a large electric cable from theris to mine lol....



cooper


Joined: 23/10/2007
Posts: 3386

Message Posted:
14/04/2008 09:31

Join or Login to Reply
Message 14 of 16 in Discussion

Thanks Kav



we are over in June and hope to sort our meter's then if ilker has done his bit.were on phase 2.



Cooper



kavenkoy


Joined: 10/04/2008
Posts: 1787

Message Posted:
14/04/2008 19:44

Join or Login to Reply
Message 15 of 16 in Discussion

if you want me to email you how to do it i will



kav



cooper


Joined: 23/10/2007
Posts: 3386

Message Posted:
14/04/2008 20:53

Join or Login to Reply
Message 16 of 16 in Discussion

Thanks Kav but Janann & Lem have already told me what to do.



Cooper