sids1969
Joined: 06/07/2007 Posts: 77
Message Posted: 06/11/2007 20:02 | Join or Login to Reply | Message 1 of 4 in Discussion |
| Hi can anyone tell us were to go for a electric meter to be fitted,as our villa is ready and we are flying out on xmas day for a week to do the snagging ect, and how long it takes for the meter and how much are they, as we will be returning back to the uk how do we know when we get a electric bill is there a direct debit we could sort out to pay things like this, many thanks cathy |
ttoli
Joined: 24/03/2007 Posts: 1172
Message Posted: 07/11/2007 12:53 | Join or Login to Reply | Message 2 of 4 in Discussion |
| Your builder should arrange this,(Check your contract), can be a drawn out affair though, Kibtec will need to inspect the wiring first, Sorry to tell you this but some have been waiting a year or more for a meter. Yes you can arrange a DD for utility bills. |
sids1969
Joined: 06/07/2007 Posts: 77
Message Posted: 07/11/2007 17:53 | Join or Login to Reply | Message 3 of 4 in Discussion |
| hi ttoli thanks for the reply, thats what we thought about the builder, as it said in our contract. he sent us an email a few days ago he is giving us a temp electric supply but then goes on by saying we need to go to the electric office ? |
ttoli
Joined: 24/03/2007 Posts: 1172
Message Posted: 07/11/2007 22:38 | Join or Login to Reply | Message 4 of 4 in Discussion |
| The builder should accompany you to the Kibtec office in town with Plans etc You'll need your Contract plus i think 170 GBP. |